According to Ju Longqing, the production director of Xiangshui Jiangsu tengkai new metal materials project, the steel structure of the plant has been completed nearly 90%, and it is expected to be completed in one month. All the key construction projects are scheduled to be carried out 24 hours a day in two shifts. According to the plan, the infrastructure construction and equipment installation will be completed in June, and the commissioning phase will begin.
The total investment of Tengkai metal new material project is 1.15 billion yuan. After all of them are put into operation, the annual output of stainless steel wire coil and small stainless steel bar can reach 300000 tons and 700000 tons respectively.